SALISBURY, MD

17.8 MW | eBOS

The project team’s challenge was to determine how to maximize system MWh production given the limited acreage and oddly shaped tree-lined site, as well as designing a cost-effective tracker foundation, given the site’s poor soils and high-water table.

Another challenge presented itself in an aggressive timeline, with construction beginning on June 15 and completion expected within 4 months. Terrasmart was able to quickly accommodate requests for design changes and deliver product within the short time span.

The project utilized Terrasmart AFCI combiners (CSK350C-32A-15-N3)